How to forecast a release completion date (ETA prediction with milestones) in Azure DevOps

:check_mark:

Forecast your Azure DevOps release completion date with Great Gadgets. Compare the ETA with milestones and review delivery and scope changes.

Context: Your team wants to estimate when the remaining release work could be completed and check whether that date aligns with the planned end date and key milestones.

A release burndown chart with an ETA forecast uses remaining work and the team’s delivery pace to estimate a completion date.

Use the Release Burndown Burnup Chart widget in Great Gadgets for Azure DevOps to display this forecast directly on your Azure DevOps dashboard.

Add the ETA forecast and release milestones

Start by configuring the widget as described in How to track release progress and scope changes in Azure DevOps. Select a shared query containing all release work items, including completed ones. Choose an estimation method, and set the release’s start date, end date, and interval length. Then add the forecast:

  1. Go to the Series tab, keep Remaining, Ideal Burndown and Scope selected, and enable Forecast Remaining and Forecast Scope.

Release burndown settings with Forecast Remaining enabled and the ideal line based on initial scope


  1. On the Forecast tab, under End date forecast based on, select The average velocity of all the completed intervals for this example.

  2. To include expected scope changes in the ETA, enable Consider the scope forecast when making the end date forecast.

  3. Under Scope forecast based on, select The average scope changes of all the completed intervals.

Release ETA settings using historical average delivery and scope changes


  1. On the Milestones tab, enable Display milestones.

  2. Here you can enter time percentage milestones, date milestones or milestones with custom labels. Choose your launch date in Date and enter a Label. Use the + button to add further milestones if needed.

Release milestone settings with a launch date and an Official Launch custom label


  1. Make sure Display the data values at the top of the chart is enabled on More Settings so the ETA is visible.

image-20261110-125333.png
  1. Save the configuration.

release-burndown-with-forecast-and-milestones.png


Interpret the chart

The dashed orange Forecast Remaining line projects the remaining work to zero. Its endpoint corresponds to the ETA at the top of the chart.

In this example, the displayed ETA is 29 December 2026, before both the planned end date of 8 January 2027 and the Official Launch milestone. The current Remaining value is also below the Ideal Burndown line, indicating that the release is progressing ahead of schedule.

Practical example

For example, if the forecast shows 29 December 2026 against a planned end date of 8 January 2027, the current estimate leaves a 11-calendar-day gap. Compare it with your Official Launch milestone too. If the ETA moves beyond that milestone, review release scope, unresolved dependencies, and team availability, then agree on a change to the plan.

Revisit the forecast as delivery pace or scope changes.

And that’s it! You can now forecast a release completion date and compare it with your planned end date and milestones directly on your Azure DevOps dashboard.

For all configuration options, see the Release Burndown Burnup Chart widget documentation.

📈