Track release progress and scope changes in Azure DevOps. Use a release burndown chart to compare remaining work with the original plan.
Context: Your team wants to see how much of a release is complete and how scope changes affect progress toward the planned end date.
A release burndown chart shows how remaining work changes over time. Displaying scope alongside it helps you understand why the amount left to finish rises or falls.
Use the Release Burndown Burnup Chart widget in Great Gadgets for Azure DevOps to display remaining work, an ideal burndown baseline, and scope changes directly on your Azure DevOps dashboard.
Configure the release burndown chart
-
Add the Release Burndown Burnup Chart widget to your Azure DevOps dashboard. See How to use Great Gadgets
-
On the configuration Data tab, select a shared query containing all work items in your release, including completed items.
-
At Time range, select Custom dates and enter the release's planned start and end dates.
-
Set Intervals of select the length of the intervals
-
At Calculate by, select your calculation method, like Story Points.
-
On the Series tab, select Remaining, Ideal Burndown, and Scope under Series to Display.
-
At Calculate the ideal series based on, select The initial scope to keep the ideal line tied to the release’s starting scope.
-
On the More Settings tab, under “Done” means, select Work item state has category “Completed”
-
Enable Show legend and Display data values at the top of the chart.
-
Save the configuration and review the chart. Remaining shows unfinished work, Scope shows the release’s total work. Compare Remaining with this baseline and check Scope when the remaining-work line changes.
Interpret the chart
Ideal Burndown (blue) shows a reference path from the initial scope to zero by the planned end date. Compare Remaining with Ideal Burndown to determine if the release is on track.
Remaining (orange) shows the unfinished story points at each point in time. It falls as work is completed and can rise when unfinished work is added or its estimate increases.
Compare the Remaining line with the Ideal Burndown line to assess progress against the original plan:
-
Remaining line is above Ideal Burndown line: More work remains than planned, indicating the project is behind schedule.
-
Remaining line is below Ideal Burndown line: Less work remains than planned, indicating the project is ahead of schedule.
-
Remaining line is aligned with Ideal Burndown line: Remaining work matches the plan, indicating the project is on track.
Scope (purple) shows the total estimated release work, including completed and unfinished work. In this example, it increases from 1,200 to 1,400 story points.
This baseline comparison helps the team review the plan; it is not an ETA forecast. To configure the chart to show an ETA Forecast see How to measure average time in state by assignee in Azure DevOps.
Practical example
For example, if 800 story points remain and 200 story points of unfinished work are added, remaining work rises to 1,000 story points. If the team then completes 200 story points, remaining work returns to 800, while Scope stays at 1,400 story points. The current Remaining value is very close to the Ideal Burndown line, indicating that the release is currently on track against the original plan.
And that’s it! You can now track remaining work, compare it with an ideal burndown baseline, and see how scope changes affect progress on your Azure DevOps dashboard.
For all configuration options, see the Release Burndown Burnup Chart widget documentation.